Gap Filler Detail

1962 – National Archives of Canada


APPENDIX "B" to
S949-105 TD2240 (CCE)
dated 14 Sep 62

Sites: Atikokan, Biscotasing, Chapleau, La Tuque, Oba, Todd Mountain, Westport Relocated.

Progress of Construction - 50% to 75%

Description of Construction Completed:

  1. Access Road - 75%

  2. Building Site - 90%

  3. Tower Foundations - 100%

  4. Radar Building - 50%

  5. Power & Accommodation Building - 50%

  6. Fuel Oil Storage Facilities - 50%

Description of Work to be Completed:

  1. Access Road - final gravelling, shaping, ditching and culverts

  2. Building Site - final grading and clean-up

  3. Radar Building - final electrical and mechanical work

  4. Power & Accommodation Building - installation of diesel alternator set and associated equipment, electrical, mechanical and plumbing work.

  5. Fuel Oil Storage Facilities - piping

  6. Security Fencing

  7. Electrical Grounding System

  8. Commercial Power (if applicable)

Time Required to Complete Construction: three to 6 months from approved DND-8 to DCL.

Status of Contracts: Terminated at above stage of completion.