Gap Filler Detail
1962 – National Archives of Canada
APPENDIX "B" to
S949-105 TD2240 (CCE)
dated 14 Sep 62
Sites: Atikokan, Biscotasing, Chapleau, La Tuque, Oba, Todd Mountain, Westport Relocated.
Progress of Construction - 50% to 75%
Description of Construction Completed:
- Access Road - 75%
- Building Site - 90%
- Tower Foundations - 100%
- Radar Building - 50%
- Power & Accommodation Building - 50%
- Fuel Oil Storage Facilities - 50%
Description of Work to be Completed:
- Access Road - final gravelling, shaping, ditching and culverts
- Building Site - final grading and clean-up
- Radar Building - final electrical and mechanical work
- Power & Accommodation Building - installation of diesel alternator set and associated equipment, electrical, mechanical and plumbing work.
- Fuel Oil Storage Facilities - piping
- Security Fencing
- Electrical Grounding System
- Commercial Power (if applicable)
Time Required to Complete Construction: three to 6 months from approved DND-8 to DCL.
Status of Contracts: Terminated at above stage of completion.