Gap Filler Detail

1962 – National Archives of Canada


APPENDIX "C" to
S949-105 TD2240 (CCE)
dated 14 Sep 62

Sites: Batchawana, Bridgetown, Lucknow, Manitouwadge, Marathon, Nipigon, Sparta, Summerville Centre

Progress of Construction - 10%

Description of Construction Completed:

  1. Access Road - 10%

  2. Building Site - 10%

  3. Tower Foundations - 10%

  4. Radar Building - 10%

  5. Power & Accommodation Building - 10%

Description of Work to be Completed:

  1. Access Road - all work except clearing

  2. Building Site - all work except clearing

  3. Tower Foundations - concrete work

  4. Radar Building - all work except foundations

  5. Power & Accommodation Building - all work except foundations

  6. Fuel Oil Storage Facilities - all work

  7. Security Fencing - all work

  8. Electrical Grounding System - all work

  9. Commercial Power (if applicable)

Time Required to Complete Construction: six to nine months from approved DND-8 to DCL.

Status of Contracts: Terminated at above stage of completion.