Gap Filler Detail
1962 – National Archives of Canada
APPENDIX "C" to
S949-105 TD2240 (CCE)
dated 14 Sep 62
Sites: Batchawana, Bridgetown, Lucknow, Manitouwadge, Marathon, Nipigon, Sparta, Summerville Centre
Progress of Construction - 10%
Description of Construction Completed:
- Access Road - 10%
- Building Site - 10%
- Tower Foundations - 10%
- Radar Building - 10%
- Power & Accommodation Building - 10%
Description of Work to be Completed:
- Access Road - all work except clearing
- Building Site - all work except clearing
- Tower Foundations - concrete work
- Radar Building - all work except foundations
- Power & Accommodation Building - all work except foundations
- Fuel Oil Storage Facilities - all work
- Security Fencing - all work
- Electrical Grounding System - all work
- Commercial Power (if applicable)
Time Required to Complete Construction: six to nine months from approved DND-8 to DCL.
Status of Contracts: Terminated at above stage of completion.