Gap Filler Detail

1962 – National Archives of Canada


APPENDIX to
Memo to DADSI
dated 10 Oct 62

GAP FILLER RADAR STATIONS,

StationBOD for
Tower Fdns
Buildings
BOD for
Commercial
Power
Remarks
Nicolet31 Jul 6331 Oct 63Where no commercial power supplied, prime power will be provided by diesel alternator sets.
Formosa31 Jul 6331 Oct 63
Tobermory31 Jul 6331 Oct 63
Scotch Settlement31 Jul 6331 Oct 63
St Joseph31 Jul 6331 Oct 63
Lac Ste Marie31 Aug 6330 Nov 63
Algonquin Park31 Aug 6330 Nov 63
Elliot Lake31 Aug 6330 Nov 63
Timmins31 Aug 6330 Nov 63
Belleterre31 Aug 6330 Nov 63
Atikokan30 Sep 6331 Dec 63
Todd Mountain30 Sep 6331 Dec 63
Westport30 Sep 6331 Dec 63
Chapleau30 Sep 63none
Biscotasing30 Sep 63none
Oba31 Oct 63none
La Tuque31 Oct 63none
Sparta31 Oct 6331 Oct 63
Lucknow31 Oct 6331 Oct 63
Bridgetown31 Oct 6331 Oct 63
Summerville Centre30 Nov 6330 Nov 63
Marathon30 Nov 63none
Manitouwadge30 Nov 6330 Nov 63
Nipigon30 Nov 6330 Nov 63
Batchawana30 Nov 63none
Hastings31 Dec 6331 Dec 63
Mattawa31 Dec 6331 Dec 63
Nobel31 Dec 6331 Dec 63
Shemogue31 Dec 6331 Dec 63
Stoney Creek31 Dec 6331 Dec 63
Beaver Tower31 May 64none
Gold Rock31 May 64none
Graham31 May 64none
L'Ascension31 May 64none
Nishkotea Lake31 May 64none
Squatteck30 Jun 6430 Jun 64
St Adalbert30 Jun 6430 Jun 64
Taschereau30 Jun 6430 Jun 64
Whitefish Lake30 Jun 64none
Whites Brook30 Jun 6430 Jun 64
Brownrigg31 Jul 64none
Gowganda31 Jul 64none
L'Anse St Jean31 Jul 64none
St Hedwidge31 Jul 64none
Eaglet River31 Jul 64noneMay be 31 Dec 63 if desired

NOTES:

  1. Above BODs are predicated on receiving financial approval by 1 Feb 63

  2. Above BODs are predicated on receiving programme approval by 1 Dec 62

  3. Above BODs are predicated on DCL awarding 45 contracts within 2 months.