S10-136-80/5 TD2269 (DCEP)
MEMORANDUM
18 Nov 63
CEP-3
Completion of Construction by CEU
Gap Filler Radar Stations, Various
There are several Gap Filler sites where the completion of construction can be most easily and economically done by CEU.
Please provide DCEM with a list of possible sites for construction by CEU next summer along with some indication of work, time and money involved.
Although we cannot provide a firm schedule, it is expected that if the program goes ahead that the first sites that can be completed for Telecom use will be the ones selected for finalization by CEU. For this reason as much advance planning as possible should be carried out this winter.
(MC Hyslop)W/C
DECP
2-5777