GAP FILLER RADAR STATIONS
Station | Preliminary Cost Estimate | Contributing Items | Remarks |
---|---|---|---|
Redditt | $153,000.00 |   |   |
Ft Francis | 164,000.00 |   |   |
Atikokan | 201,000.00 | $39,000.00 | Access rd 1.5 miles |
Graham | 234,000.00 | 144,000.00 | Larger Building 3 APUs |
Silver Falls | 152,000.00 |   |   |
Nipigon | 361,000.00 | 153,000.00 | Access Rd 8 miles |
Geraldton | 176,000.00 |   |   |
Marathon | 305,000.00 | 98,000.00 | Access Rd 3.5 miles |
  |   | 138,000.00 | Larger Building 3 APUs |
Eaglet River | 417,000.00 | 150,000.00 | Access Rd 3 mi & wharf |
  |   | 180,000.00 | Larger Building 3 APUs |
Oba | 245,000.00 | 162,000.00 | Larger Building 3 APUs |
Batchawana | 288,000.00 | 144,000.00 | Larger Building 3 APUs |
  |   | 85,000.00 | Power Line between Bldgs |
Chapleau | 161,000.00 |   |   |
Timmins | 155,000.00 |   |   |
Biscotasing | 224,000.00 | 150,000.00 | Larger Building 3 APUs |
Elliot Lake | 174,000.00 |   |   |
Tobermory | 118,000.00 |   |   |
Nobel | 136,000.00 |   |   |
Algonquin Park | 196,000.00 |   |   |
Buckhorn | 115.000.00 |   |   |
Belleterre | 241,000.00 | 150,000.00 | Larger Building 3 APUs |
Lac des Loups | 227,000.00 | 150,000.00 | Larger Building 3 APUs |
Lac Ste Marie | 209,000.00 | 32,000.00 | Access Rd 2.7 miles |
La Macaza | 256,000.00 | 38,000.00 | Access Rd 2.6 miles |
  |   | 60,000.00 | Power Line to site |
La Tuque | 241,000.00 | 34,000.00 | Access Rd 6.8 miles |
  |   | 138,000.00 | Larger Building 3 APUs |
Nicolet | 118,000.00 |   |   |
Ste Cecile | 262,000.00 | 38,000.00 | Access Rd 1.5 miles |
  |   | 85,000.00 | Power Line between Bldgs |
Portneuf | 385,000.00 | 50,000.00 | Bridge over Portneuf River |
  |   | 105,000.00 | Access Rd 3.5 miles |
  |   | 162,000.00 | Larger Building 3 APUs |
St Cleophas | 230,000.00 | 30,000.00 | Access Rd 3 miles |
  |   | 65,000.00 | Power Line to site |
Mt Carleton, PQ | 232,000.00 | 55,000.00 | Access Rd 3.5 miles |
Les Etroits | 247,000.00 | 48,000.00 | Access Rd 5 miles |
  |   | 65,000.00 | Power line to site |
Mt Carleton NB | 325,000.00 | 52,000.00 | Access Rd 6 miles |
  |   | 162,000.00 | Larger Building 3 APUs |
Todd Mountain | 222,000.00 | 28,000.00 | Access Rd 9.5 miles |
  |   | 61,000.00 | Power line to site |
Alder River | 154,000.00 |   |   |
New Yarmouth | 220,000.00 | 85,000.00 | Power line between bldgs |
St Joseph | 123,000.00 |   |   |