In reply to your letter File 10-80/5 (JDPG) dated 4 January 1960 the following progress report is submitted:
Site | Field Survey Report | Remarks |
---|---|---|
Todd Mountain, NB | Completed | Submitted to AFHQ |
St Joseph, NS | Completed | Submitted to AFHQ |
Les Etroits, NB | Completed in draft form | To be submitted by 15 Jan 60. |
Alder River, NS | 90% complete in draft form | Awaiting info re forest fire hazard. To be submitted by 30 January 1960. |
Mount Carleton, NB | 10% completed in draft form Free hand siting sketch required | To be submitted by 20 January, 1960 |
New Yarmouth, NS | 80% completed in draft form | Awaiting fire tower data from Minas Basin Paper Company. To be submitted by 30 Jan 60. |
All reports will be submitted to AFHQ by 30 January 1960. Siting drawings has been completed on all sites and minor additions to the drawings, as noted in your letter 10-T54 (JDPG) dated 24 December 1959 have been completed on all sites except Mount Carleton.
Sincerely yours
WH CRANDALL & ASSOCIATES
AJ Hiscock, MA Sc, P Eng.