Gap Filler Detail

1960 – National Archives of Canada


S10-136-80/5 TD0007A

William H Crandall & Associates
Consulting Engineers
PO Box 36
Moncton, NB

SECRET

January 6, 1960

Chief of Air Staff
Air Force Headquarters
Ottawa, Ontario

Attention: CCE Victoria Island

Re: Gap Filler Stations Maritimes Field Survey Report

Dear Sir:

In reply to your letter File 10-80/5 (JDPG) dated 4 January 1960 the following progress report is submitted:

SiteField Survey ReportRemarks
Todd Mountain, NBCompletedSubmitted to AFHQ
St Joseph, NSCompletedSubmitted to AFHQ
Les Etroits, NBCompleted in draft formTo be submitted by 15 Jan 60.
Alder River, NS90% complete in draft formAwaiting info re forest fire hazard. To be submitted by 30 January 1960.
Mount Carleton, NB10% completed in draft form
Free hand siting sketch required
To be submitted by 20 January, 1960
New Yarmouth, NS80% completed in draft formAwaiting fire tower data from Minas Basin Paper Company. To be submitted by 30 Jan 60.

All reports will be submitted to AFHQ by 30 January 1960. Siting drawings has been completed on all sites and minor additions to the drawings, as noted in your letter 10-T54 (JDPG) dated 24 December 1959 have been completed on all sites except Mount Carleton.

Sincerely yours

WH CRANDALL & ASSOCIATES

AJ Hiscock, MA Sc, P Eng.