TD9286
William H Crandall & Associates
Consulting Engineers
PO Box 36
Moncton, NB
October 7, 1959
SECRET
Chief of the Air Staff,
Air Force Headquarters,
Ottawa, Ont
Dear Sir:
Re: Progress Report No 2,
Maritime Gap Filler Stations.
Further to our Progress Report No 1, dated 14 September the following additional work has been completed during the period 7 September to 1 October 1959.
No change. Reconnaissance of St Joseph's and Alder River will be completed by 16 October 1959.
Mount Carleton, NB
Les Etroits, NB. Field Survey started 28 September 1959. Building site survey (brick, monuments, etc) completed. Access Road Survey in progress, 10% completed. Estimated completion date 24 October 1959.
Siting instruction plan on line, scale 1" equals 50' completed for the following: Mount Carleton.
Foundation sketches for the following soil conditions have been prepared:
No further foundation sketches will be prepared as per your letter S10-136-80/5 (JDPG) dated 5 October 1959.
Sincerely yours,
W H CRANDALL & ASSOCIATES,
A J Hiscock, MA Sc, P Eng.