Gap Filler Detail

1959 – National Archives of Canada


S10-136-80/5 TD 9331

William H Crandall & Associates
Consulting Engineers
PO Box 36
Moncton, NB

SECRET

Chief of the Air Staff,
Air Force Headquarters,
Ottawa, Ont

Attention: CCE Victoria Island

Dear Sir:

Re: Progress Report No 3, Maritime Gap Filler Stations

Further to our Progress Report No 2, dated 7 October, enclosed please find a Progress Report covering work completed to 15 November 1959.

  1. Site Reconnaissance, Reconnaissance Report & Intermim Construction Estimate

    Completed for all 6 sites.

  2. Field Survey (Completed)

    Completed for all 6 sites.

  3. Field Survey Plans

    Siting instruction plans on linen, scale 1" equals 50 ' completed for 5 sites.

    Plan for Alder River being prepared (10% completed).

  4. Foundation sketches for Building & Towers

    No additional work carried out, as per your letter S10-136-80/5 (JDPG) dated 5 October 1959.

  5. Field Survey Report

    Field Survey Report on Todd Mountain being drafted. To be submitted for review by 3 December 1959.

Sincerely yours,

W H CRANDALL & ASSOCIATES
AJ Hiscock, M A Sc, P Eng.