MEMORANDUM

29 Nov 63

Ref: 10-36-80/5 (DCEP) 15 Nov 63
10-36-80/5 (Eng-4) 20 Nov 63

D Arch C

Completion of Plans & Specifications
Gap Filler Radar Stations, Various

Based on tentative target dates for the completion of the road work on the various projects within the Eng-4 Section, the following are suggested target dates for the completion of specifications and estimates:

Week EndingStation
Dec 13/63Sparta
Dec 20/63Beaver Tower
Jan 10/64Graham
Jan 17/64Taschereau
Jan 24/64Nishkotea Lake
Jan 31/64La tuque
Feb 7/64St Hedwidge
Feb 14/64Hastings & Atikokan
Feb 21/64Gowganda
Feb 28/64Stoney Creek & Biscotasing
Mar 6/64L'Ascension
Mar 13/64Nobel
Mar 20/64Mattawa
Mar 27/64Chapleau & Westport

Major jobs have been allocated one week each, minor jobs have been allocated one-half week each. There is on specific priority at this time as long as one major job or two minor jobs are finished each week. The possibility of a speed up must be kept in mind if approval is received to proceed to contract and this becomes a crash programme.

(MC Hyslop) W/C
DCEP
2-5777