Gap Filler Detail

1960 – National Archives of Canada


GENERAL ENGINEERING COMPANY
LIMITED
CONSULTING ENGINEERS
100 Adelaide Street West,
Toronto 1, Ont.

File No:10-36-80/5 (JDPG)

February 24, 1960

Chief of the Air Staff,
Air Force Headquarters,
Ottawa, Ontario

Attention: CCE, Victoria Island

Dear Sir:

Re: Gap Filler Stations - NE Ontario

We have been somewhat delayed in the completion of the first stage of the above note project.

Although we are aware that you only require the 1" = 50' plan to be completed at this time, we have had to practically complete the 1" = 200 ft plan as well, in order to be able to show sufficient detail for estimating.

The situation with regard to the various sites is as follows:

  1. 1" = 50' plan completed for all sites
  2. 1" = 200' plan virtually completed for all sites except Chapleau
  3. Field report drafted for all sites and completed for Elliot Lake
  4. Rough design sketches for Elliot Lake to be completed this week, and the remainder by March 25th
  5. Reports for all sites typed and forwarded to Air Force Headquarters by March 24th.

Having reviewed the remaining funds available for this project, we find that while we still have funds in hand, we will have to make a submission for an additional $2,910.00. This will be done forthwith.

Yours very truly,

GENERAL ENGINEEERING COMPANY LTD

RMP Hamilton