MICKELSON, FRASER & HAYWOOD
ENGINEERS AND ARCHITECTS
PO Box 186 Fort William, Ont
September 24, 1959
Chief of the Air Staff,
Air Force Headquarters
Ottawa, Ontario
Attention: CCE - Victoria Island
Dear Sirs:
Re: Preliminary Engineering Services,
Gap Filler Radar Stations,
Northwestern Ontario
Reference:10-36-80/5 (JDPG)
With reference to the last sentence of your letter dated September 22nd, File No 10/N19 (JDPG), we attach hereto a chart showing the work completed under our contract to date.
We are currently preparing the reconnaissance reports on the Fort Frances and Redditt sites, and proceeding with the preparation of the survey drawings for the Silver Falls site. We expect to have completed reconnaissance visits to the three remaining sites by the end of September.
Yours truly,
MICKELSON, FRASER & HAYWOOD,
per RA Campling.
MICKELSON, FRASER & HAYWOOD
ENGINEERS AND ARCHITECTS
PO Box 186 Fort William, Ont
September 24, 1959
PROFESSIONAL ENGINEERING SERVICES
GAP FILLER RADAR SITES
NORTHWESTERN ONTARIO
PROGRESS RECORD
  | Recce Trip | Recce Report | Field Survey | Survey Dwg | Survey Report |
---|---|---|---|---|---|
Fort Frances | 23/9 |   |   |   |   |
Redditt | 14/9 |   | 24/9 |   |   |
Atikokan | 14/7 | 15/9 |   |   |   |
Graham |   |   |   |   |   |
Silver Falls | 2/9 | 15/9 | 7/9 |   |   |
Nipigon | 3/9 | 15/9 |   |   |   |
Geraldton |   |   |   |   |   |
Marathon |   |   |   |   |   |