MICKELSON, FRASER & HAYWOOD
ENGINEERS AND ARCHITECTS
PO Box 186 Fort William, Ont
October 8, 1959
Chief of the Air Staff,
Air Force Headquarters
Ottawa, Ontario
Attention: CCE - Victoria Island
Dear Sir:
Re: Gap Filler Radar Stations
Northwestern Ontario
Ref S10-136-80/5 (JDPG)
With reference to General Instruction #1, dated October 5, 1959, the following work remains to be done in the reconnaissance stage of our preliminary engineering services contract. The dates by which the work is expected to be completed are tabulated.
Job No | Reconnaissance Visit | Reconnaissance Report and Interim Construction Estimate |
---|---|---|
5063 |   | October 15, 1959 |
5077 |   | October 15, 1959 |
5073 | October 14, 1959 | October 17 1959 |
5074 | October 14, 1959 | October 17, 1959 |
Yours very truly,
MICKELSON, FRASER & HAYWOOD
per RA Campling