Gap Filler Detail

1963 – National Archives of Canada


10-36-80/5 (CCE/Prop)

MEMORANDUM

4 Apr 63

ADM(C&P)

Utilities Policy - Gap Filler Programme-
Commercial Power Requirements

In accordance with the recent policy decision affecting the schedule of the subject programme and as directed by item 10 of minutes of CCE Staff Meeting No 120 held on 14 Feb 63, the potential suppliers of electrical energy to the Gap Filler sites are being advised that there will be no power requirement for this year and that notification will be given if a requirement should arise at a later date.

If you concur may the several letters at flyleaf by signed and despatched, please. Kindly note that two of the letters are recommended for translation into the French language (Tagged X).

(JF Brennagh) W/C
for CAS