10-36-80/5 (ATSC)
Ottawa, Ont
2 Dec 59
Commander
Ground Electronics Engineering-Installation Agency
Griffiss Air Force Base
New York.
Attn: ROZMA-CADIN
Gap Filler Radar Layout in Armco Building
As agreed at our meeting on 19 Nov 59, the following Armco drawings are forwarded for your use in preparing revised equipment layout of gap filler radar in an Armco building:
Instruction Sheet No | Title & Remarks |
---|---|
E2-1E | Typical Details, showing wall, roof and ceiling construction |
E2-2 | Building Layout (see E2-7EE) |
E2-3 | Base Channel Layout. Note "L" and "W" are out to out of building and inside dimensions are 6-1/4" less. |
E2-4 | Wind Bent Layout. Number of wind bents will depend on length of building, probably one only. |
E2-5 | Wind Bent Assembly. It is o be noted that this would be the only obstruction within the building. |
E2-6 | Wall Panel Erection, showing method of erecting 16" panels. Interior will be finished with dry-wall construction. Clear ceiling height of 10'0" can be provided using 10'9-1/4" panels in RCAF Stock. |
E2-7EE | Wind Bracing Layout. Note that lay length can be 6'8", 8'10", 9'4", 10'8" or 12'0", therefore, length of building could be 40'0" or as required by equipment. |
(DV Marks) Maj
for CAS