Re: Progress Statement No 11
Gap Filler Radar Stations
Southern Ontario
Dear Sir:
As directed in your Statement of Services revised 10 July 1959, Page 7, para (f), we submit herewith two (2) copies of our Progress Statement covering the period of Progress Claim No 12.
Yours very truly,
MM DILLON & COMPANY LIMITED
G M Burns, P Eng,
Project Manager.
M M DILLON & COMPANY LIMITED
CONSULTING ENGINEERS
LONDON, TORONTO, OTTAWA, WINDSOR
GAP FILLER RADAR STATIONS
SOUTHERN ONTARIO
PROGRESS STATEMENT NO 11
AS OF 31 AUGUST 1961
COVERS PERIOD OF PROGRESS CLAIM NO 12
PHASE I
RCAF JOB NO | MMD JOB NO | RECONNAISSANCE | FIELD SURVEY | REPORT | REMARKS | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Start | % Comp | Est Compl | Start | % Comp | Est Compl | Start | % Compl | Est Compl | |||
5066 | 5678 -1 | - | 100 | - | - | 100 | - | - | 100 | - |   |
5051 | -2 | - | 100 | - | - | 100 | - | - | 100 | - |   |
5048 | -3 | - | 100 | - | - | 100 | - | - | 100 | - |   |
5053 | -4 | - | 100 | - | - | 100 | - | - | 100 | - | Original Site Abandoned Relocated Site |
5050 | -5 | - | 100 | - | - | 100 | - | - | 100 | - | Abandoned |
5046 | -6 | - | 100 | - | - | 100 | - | - | 100 | - |   |
5966 | -9 | - | 100 | - | - | 100 | - | - | 100 | - |   |
5974 | -8 | - | 100 | - | - | 100 | - | - | 100 | - |   |
5963 | -10 | - | 100 | - | - | 100 | - | - | 100 | - |   |
5972 | -11 | - | 100 | - | - | 100 | - | - | 100 | - |   |
PHASE II
RCAF JOB NO | MMD JOB NO | DESIGN INC SITE MODF'N | DRAWINGS | SPECIFICATIONS | REMARKS | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Start | % Comp | Est Compl | Start | % Comp | Est Compl | Start | % Compl | Est Compl | |||
5066 | 5678 -1 | - | 100 | - | - | 100 | - | - | 100 | - | 100% except for negotiations with HEPC |
5051 | -2 | - | 100 | - | - | 100 | - | - | 100 | - | 100% except for negotiations with HEPC |
5048 | -3 | - | 100 | - | - | 100 | - | - | 100 | - | 100% except for negotiations with HEPC |
5053 | -4 | - | 100 | - | - | 100 | - | - | 100 | - | 100% except for negotiations with HEPC |
5050 | -5 | - | - | - | - | - | - | - | - | - | Abandoned |
5046 | -6 | 28 Dec 60 | 70 | 15 Sept | 27 Dec 60 | 75 | 15 Sept | 2 Aug 61 | 55 | 15 Sept |   |