Gap Filler Detail
1962 – National Archives of Canada
10-36-80/5 (DCEP)
MEMORANDUM
29 Jan 62
Chief/Inspection
7 Inspectors
Access Roads
Gap Filler Radar Stations - General
During the field inspections of the Gap Filler Radar Stations, it is requested that the following questions be answered and the Project Officer advised:
- Who is laying out the alignment and grades for the access road:
- Is he experienced with road construction?
- Are plan, profile and cross sections being prepared for construction and payment?
- Are adjustments being made to alignment and finshed grade elevations to economize?
- Is an overrun anticipated in road quantities, especially rock excavation?
- Is clearing being done well ahead of road construction and completed, including disposal of timber, brush, trimmings and stumps?
- Is the right-of-way being kept cleaned up, trees not being bulldozed down the slopes and living trees beyond the right-of-way not being damaged?
- What is the condition of road between highway and beginning of new construction?
(WR Alexander)
CEP-3-3
2-6558