Gap Filler Detail

1962 – National Archives of Canada


10-36-80/5 (DEngC)

MEMORANDUM

27 Nov 62

DCEP

Access Roads

Project files have been received for the construction of access roads to the following Gap Filler Sites:

PF #2204L'Anse St JeanPF # 2201Gold Rock
#1309Graham#2199Beaver Tower
#2218White Fish Lake#2217Whites Brook
#2513St Hedwidge#2216Taschereau
#2213Squatteck#2209Nishkotea Lake

Before carrying out detailed checking of the consultant's designs for these roads, an examination was made of the cost of access roads now under construction for the Gap Filler Programme. Data provided by the project officer is appended. This includes the contract awards together with the amounts claimed to date and an estimated unit price per mile for the roads. It is interesting to note that at sites where rock was encountered, the unit cost is approximately $40,000 to $50,000 per mile, and at the sites where rock was not encountered the unit price is running approximately $20,000 to $30,000 per mile.

It is apparent that by producing detailed plans and specifications, the standard of road being built is in excess of that required for normal access to the sites by tracked vehicles.

It is proposed therefore that consideration be given to the award of lump sum contracts for the construction of the Gap Filler sites complete with services. As an overhead cost the contractor should be asked to include a sum for clearing a construction trail into the site. A suggested route for the construction access road could be included with the SIP for the Gap Filler Sites.

Upon completion of the site, a survey of the construction access road could then be carried out and any improvements to this road could be carried out either as a second contract or as an extension to the original contract.

This proposal would force the contractors to construct the most economic access to the site and this might meet the RCAF requirement. Hence some of the large costs, especially in areas that do not involve rock excavation, could be reduced.

May this proposal be considered and advice forwarded to DEngC before a great deal of engineering work is carried out examining the present project files.

(GS Galley) W/C
Acting/DEngC
2-6246


Cost of Access Roads

SITECONTRACT
VALUE
AMT CLAIMEDUNIT PRICE PER
MILE
COMMENTS
Algonquin 38,86426,33742,500All New
Atikokan60,13241,79929,900All New
Batchawana78,78046,05320,400All New
Belleterre30,88121,90715,000All New
Biscotasing23,95418,7428,650All New
Bridgetown14,54314,55021,200All New
Elliot Lake19,77019,77022,000All New
Lac Ste Marie96,0006,01533,200All New
La Tuque70,71058,90350,000(est)New Portion
Manitouwadge33,73421,44638,000All New
Marathon125,24476,80843,500All New
Nipigon156,943114,88735,000 (Est)New Portion
Oba71,15071,50336,700All New
Scotch Settlement18,57718,70435,000(Est)New Portion
Timmins21,73519,74914,500All New
Todd Mtn51,84848,8456,000All New