SECRET
S10-136-80/5 (DCEP)
Victoria Island,
Ottawa, Ontario
9 February 1961
Defence Construction (1951) Limited
56 Lyon Street
Ottawa, Ontario
Attention: Mr A G Bland
Re: Proposed Tender Calls, Spring 1961
Gap Filler Radar Stations, General
Dear Sirs:
In order for Defence Construction Limited to be aware of the general impact of the Gap Filler Radar Stations Programme, we wish to take this opportunity of advising you of the following details.
Yours truly,
(JW Griffith)
Group Captain
for Chief of the Air Staff
SECRET
APPENDIX to
S10-136-80/5 (DCEP)
9 February 1961
Station | Description of Access Road |
---|---|
Nobel, Ont | Access road 600 ft directly from highway |
Nicolet, Que | Access Road 300 directly from township road |
Tobermory, Ont | Access Road 3,000 ft existing road and 300 ft new road |
St Joseph, NS | Access Road 600 ft directly from township road |
Formosa Rel, Ont | Access Road 0.3 miles new road |
Scotch Settlement Rel NB | Access Road 7,000 ft existing road and 1,000 ft new road |
Lac Ste Marie, Que | Access Road 6.2 miles existing road and 2.6 miles new road. Clearing. Rock. |
Algonquin Park, Ont | Access Road 2,400 ft directly from highway. Clearing. |
Elliot Lake, Ont | Access Road 1.3 miles major improvement |
Oba, Ont | Access Road 1.5 miles new road from CNR. |
Chapleau, Ont | Access Road 6 miles existing road and 500 ft new road from CP Railway |
La Tuque | Access Road 19.2 miles existing road and 0.8 miles new road. (Ferry over St Maurice River). |
Todd Mtn, NB | Access Road 8.5 miles major improvement. |
Timmins, Ont | Access Road 2,000 ft minor improvement and 5,000 ft new road. Clearing. Rock. |
Belleterre, Que | Access Road 1.8 miles existing road and 1.3 miles new road. |
Nipigon, Ont | Access Road 7.5 miles minor improvement and 1.5 miles new road. Clearing. Rock. |
Atikokan, Ont | Access Road Access Road 1.3 miles existing road and 0.8 miles major improvement on existing trail. Clearing. Rock. |
Westport, Ont | Access Road 1.0 miles major improvement and 0.5 miles new road. |
Biscotasing, Ont | Access Road 4 miles new road from CP Railway. Clearing. |
Marathon, Ont | Access Road 2.85 miles new road. Clearing. Rock. |
Batchawana, Ont | Access Road 16.46 miles existing logging road and 4.2 miles new and major improvement on existing trails. Clearing. Rock. |