February 3, 1960
Chief of the Air Staff
Airforce Headquarters
Ottawa, Ontario
Attention: CCE - Victoria Island
Dear Sir:
Re: Gap Filler Radar Stations,
Northwestern Ontario
Preliminary Engineering Services
Reference: S10-136-80/5 (JDPG)
We enclose Progress Chart for this project for the period ending January 31, 1960.
At present the field survey crew is on the Fort Frances site and we expect the survey to be completed about the 15th of February, which wil substantially complete the outside work for all sites.
From now on we will concentrate on the survey drawings and survey reports and endeavour to have all the work completed by the early part of March.