Gap Filler Detail

1961 – National Archives of Canada


July 4, 1961

DEPARTMENT OF NATIONAL DEFENCE
GAP FILLER STATIONS, NE ONTARIO
TIMMINS STATION, JOB NO 5069

Sheet No 1 & 2

FINAL CONSTRUCTION ESTIMATE

RADAR BLDG: Special Foundation$2,580.00
POWER & ACCOMMODATION BLDG: Special Foundation2,615.00
TOWER: Special Foundation880.00
PASSAGEWAY: Foundation, Structure & Sheathing480.00
CLEARING, GRUBBING & GRADING

  1. Clearing:
    On Site - 8.8 acres
    Access Road - 10.0 acres
    Total - 18.8 acres - @ $400.00 -$7,520.00

  2. Close Cutting:
    On Site - 7.2 acres
    Access Road - 5.8 acres
    Total - 13.0 acres - @ $325.00 -$4,225.00

  3. Grubbing:
    On Site - 1.6 acres
    Access Road - 5.0 acres
    Total - 6.6 acres - @ $200.00 -$1,320.00

  4. Grading:
    On Site - 0.4 acres
    Access Road - 0 acres
    Total - 0.4 acres - @ $150.00 -$60.00

  5. Brush Control:
    On Site - 7.2 acres
    Access Road - 6.1 acres
    Total - 13.3 acres - @ $70.00 -$931.00

Total Area Treated 18.8 acres
$14,056.00
ACCESS ROAD:
  1. Common Excavation incl cut and fill - 13,200 cu yds @$0.60 - 47,920.00
  2. Rock Excavation incl Boulders - 200 cu yd @$5.00 - $1,000.00
  3. Supply and Placing Borrow for Sub-Grade - 4,900 cu yd @ $0.50 - $2,450.00
  4. Supply and Placing of Granular Base Course - 2,450 cu yd @ $0.65 - $1,593.00
  5. Compaction of Granular Base Course - 14,600 sq yd @ $0.25 - $3,650.00
  6. Supply and Installation of Culverts:
    24"ø x 100 Lin Ft @ $6.50 - $650.00
    12"ø x 30 Lin Ft @ $3.50 - $105.00

Total 1.5 Mile Access Road
$17,368.00
BULK FUEL FACILITIES
Including special Foundation, Pipe Supports, Piping. (not included are Tank and Pump)
220.00
SECURITY FENCING

  1. Fence including Fabric, Top Rail Arms, Barbed Wire, Line Posts, Footings, all Fittings, etc
    988 Lin Ft @ $3.50 - $3,458

  2. Gate Posts 4 1/2"ø with Braces and Footings -
    2 each @ $30.00 - $60.00

  3. Corner or Straining Posts with Braces and Footings
    4 each @ $38.00 - $152.00

  4. Gate (Standard) with 3 rows of Barbed Wire and necessary Fittings -
    12 Lin Ft @ $7.50 - $90.00

  5. Section Crossing Ditch, extra - 0

  6. Footing in Partial Rock, extra -
    100 each @ $3.00 - $300.00

Total 1,000 ft of Fencing -

$4,060.00
GROUNDING SYSTEM750.00
SANITARY DRAIN20.00
INSTALLATION OF DIESEL(S)NIL
FARM FENCINGNIL
TOTAL (not including any Equipment, Work or Operations covered under Standard Specs)$43,029.00