Gap Filler Detail

Status of Gap Filler Sites - 1962 – National Archives of Canada


When replying refer to file 122-7-193-S41-1

INTER-OFFICE MEMO
DEFENCE CONSTRUCTION (1951) LIMITED

Date: Aug 1st, 1962

To: Mr LD Birden,
Construction Engineer

From: DE Bastedo

Re: Gap Filler Program,
Atlantic Region

Status of Gap Filler Sites as at August 3rd, 1962, will be as follows:

Scotch Settlement

Completion of job is close. Buildings, tower foundation and road are completed except for minor sub trade work.

Todd's Mountain

Road will be completed by this date. Tower foundations are complete and building is erected. Mechanical and Electrical trades are awaiting materials but should be completed in four weeks.

Saint Joseph

All portions of work are essentially completed.

Bridgetown

Building excavation completed. Road is completed except for gravelling. Building components are not on site.

Summerville Centre

Road is completed and some work on Tower foundations and Building footings have been done. Building components are not on site but are required next week.

DE Bastedo, P Eng
Branch Manager

DEB/sp