When replying refer to file 122-7-193-S41-1
INTER-OFFICE MEMO
DEFENCE CONSTRUCTION (1951) LIMITED
Date: Aug 1st, 1962
To: Mr LD Birden,
Construction Engineer
From: DE Bastedo
Re: Gap Filler Program,
Atlantic Region
Status of Gap Filler Sites as at August 3rd, 1962, will be as follows:
Scotch Settlement
Completion of job is close. Buildings, tower foundation and road are completed except for minor sub trade work.
Todd's Mountain
Road will be completed by this date. Tower foundations are complete and building is erected. Mechanical and Electrical trades are awaiting materials but should be completed in four weeks.
Saint Joseph
All portions of work are essentially completed.
Bridgetown
Building excavation completed. Road is completed except for gravelling. Building components are not on site.
Summerville Centre
Road is completed and some work on Tower foundations and Building footings have been done. Building components are not on site but are required next week.
DE Bastedo, P Eng
Branch Manager
DEB/sp