122-7-193-09-1
Aug 9/62
Mr JD McIlveen,
Branch Manager,
Toronto, Ont
Gap Filler - Oba
Please refer to your status report dated July 31st.
The passageway roofing and siding should be completed to provide secure storage in the buildings for materials and equpment on site but not installed. The fencing need not be started. The deletion set forth in your recommendations are acceptable with the addition of the fencing.
LD Briden,
Assistant Chief Engineer,
(Field Project)