BELLETERRE, PQ
File 122-7-193-B18-1
Contractor | Jolliette & Mercier Inc |
Awarded | December 15, 1961 |
Contract comp date | July 31, 1962 |
Value of contract | $131,000.00 |
Value of work completed July 31, 1962 | $100,000.00 |
Current estimated completion date | September 30, 1962 |
Access Road | Rough grading complete Base course underway - should be completed by August 10/62 |
Tower Fnds | Complete |
Tower Erection | Not started |
Acc Bldg | Fnds complete Floor slab complete Steelox Bldg erected and lined Floor tile underway Electrical 30% complete Mechanical - not started |
Radar Bldg | Same status as Acc Bldg |
Passageway | Complete except for door and electical fixtures |
Building Site | Rough grading done Fencing on site - to commence August 6, 1962. |
Fuel Tanks | 50,000 gal - erected and primed dyke not complete 2000 gal - tank in place Piping is not done. Pipe supports to be constructed this week with piping to be complete by August 15. |
Diesel Generator | Not on site - expected in 2 weeks. |
Recommendation re termination of contract:
Contractor should be instructed to cease work at once, except that fence should be erected for security. Building to be locked up. Diesel Generator and radar tower to be held in RCAF storage.