Gap Filler - Biscotasing

Please refer to your status report dated July 31st.

In respect to the accommodation building, particularly the electrical, mechanical and the painting these items should not proceed, nor should the fencing or the brush control, the 5000 gallon tank and the 2000 gallon tank. We will, however, complete the roofing and the siding of the passageway so that the buildings can be closed up and any construction materials or equipment that has reached the site can be safely stored withing. The diesel generator will not be shipped.

LD Briden,
Assistant Chief Engineer,
(Field Project)