SPARTA
File 62-702-S42-1
Contractor | Ellis-Don Limited |
Awarded | June 1, 1962 |
Contract comp date | Aug 31, 1962 |
Value of contract | $56,000.00 |
Value of work completed July 31, 1962 | $8,000.00 |
Current estimated completion date | September 30, 1962 |
Access Road | Subgrade 60% complete |
Tower Fnds | Footings poured and piers formed |
Tower Erection | Not started |
Acc Bldg | Fnd walls poured |
Radar Bldg | Fnd wall poured Fnd grounding system installed |
Passageway | Not started |
Building Site | 20% of rought site grading complete Fence material not on site |
Fuel Tanks | 2000 gal tank not on site No work on foundations |
Diesel Generator | Not on site |
Steelox Buildings | Ordered but not released by RCAF |
Land Option | Farmer-Owner advises Proj Eng that DOT have not concluded land acquistion arrangements. |
Recommendation re termination of contract:
The contractor should be notified to cease work at once. The site can be restored to its orginal condition except for tree removal. If work is to proceed, then immediate arrangements must be made to get Steelox components to site not later than August 15, 1962.