TOBERMORY
File 122-7-193-T10-1
Contractor | Logan Const |
Awarded | November 3, 1961 |
Contract comp date | June 30, 1962 |
Value of contract | $54,000.00 |
Value of work completed July 31, 1962 | $52,000.00 |
Current estimated completion date | August 15, 1962 |
Access Road | Complete |
Tower Fnds | Complete |
Tower Erection | Not started |
Acc Bldg | Complete |
Radar Bldg | Complete |
Passageway | Complete |
Building Site | Complete |
Fuel Tanks | Complete |
Diesel Generator | On site, now being hooked up |
Recommendation re termination of contract:
All work should be completed except installation of radar tower.