FORMOSA
File 122-7-193-A15-1
Contractor | Logan Const |
Awarded | November 3, 1961 |
Contract comp date | July 15, 1962 |
Value of contract | $55,000.00 |
Value of work completed July 31, 1962 | $45,000.00 |
Current estimated completion date | August 21, 1962 |
Access Road | 95% complete |
Tower Fnds | Complete |
Tower Erection | Not started |
Acc Bldg | Complete except for minor electrical and painting |
Radar Bldg | Same status as Acc Bldg |
Passageway | Complete |
Building Site | Rough grading complete fence not erected |
Fuel Tanks | 2000 gal tank in place connection not complete |
Diesel Generator | Expected on site any day |
Recommendation re termination of contract:
All work should be completed except installation of diesel generator and radar tower.