LAC STE MARIE, PQ
File 122-7-193-l15-1
Contractor | Quemont Enterprises |
Awarded | November 3, 1961 |
Contract comp date | July 31, 1962 |
Value of contract | $170,000.00 |
Value of work completed July 31, 1962 | $140,000.00 |
Current estimated completion date | August 31, 1962 |
Access Road | Complete except final re-shaping |
Tower Fnds | Complete |
Tower Erection | Not started |
Acc Bldg | Bldg complete, Elect & Mech 80% Painting - not started - materials on site |
Radar Bldg | Same status as Acc Bldg |
Passageway | Complete |
Building Site | Rough grading complete Fencing underway Brush control not done |
Fuel Tanks | 10,000 gal tank installed, tested and hooked up |
Diesel Generator | To be delivered to site approx August 6, 1962. |
Recommendation re termination of contract:
Contractor should be instructed to complete all work excepting:
Radar tower should not be installed.