ALGONQUIN PARK
File 122-7-193-A15-1
Contractor | M J Sulpher |
Awarded | January 26, 1962 |
Contract comp date | June 30, 1962 |
Value of contract | $104,000.00 |
Value of work completed July 31, 1962 | $85,000.00 |
Current estimated completion date | August 31, 1962 |
Access Road | Complete |
Tower Fnds | Complete |
Tower Erection | Not started |
Acc Bldg | Fnds complete Floor slab complete Steelox Bldg erected with liner and ceiling panels in place Electrical - not started Mechanical - not started Painting - not started. |
Radar Bldg | Same status as Acc Bldg |
Passageway | Fnds and floor slab poured Framing complete Roofing and sheeting not started |
Building Site | Rough Grading complete Fencing about 90% complete Brush control complete |
Fuel Tanks | Fnds complete 2000 gal tank in place piping not started |
Diesel Generator | Not on site - expected any day |
Recommendation re termination of contract:
All work should be completed except:
Hand written note: items 1 to 4 completed