ELLIOT LAKE
File 122-7-193-E12-1
Contractor | Carrington Construction |
Awarded | December 5, 1961 |
Contract comp date | July 31, 1962 |
Value of contract | $96,000.00 |
Value of work completed July 31, 1962 | $90,000.00 |
Current estimated completion date | August 21, 1962 |
Access Road | Complete |
Tower Fnds | Complete |
Tower Erection | Not started |
Acc Bldg | Complete except for floor tile and painting grounding 95% |
Radar Bldg | Same as for Acc Bldg |
Passageway | Complete |
Building Site | Complete |
Fuel Tanks | 2,000 gal tank completed |
Diesel Generator | Expected on site Aug 1/62 |
Recommendation re termination of contract:
All work should be completed except installation of diesel generator and Radar Tower.