1 Dec 59

Operations – Routine operations, 16 practice intercepts.

Telecommunications – Communications section was moved to new quarters on third floor.

2 Dec 59

Operations – STP problem and Broadcast Control exercise carried out. 36 practice intercepts.

Recreation – Station bingo held tonight.

3 Dec 59

Operations – Routine operations, 18 intercepts attempted.

4 Dec 59

Operations – Broadcast Control exercise, 36 intercepts attempted.

Construction & Engineering – Station took over a newly installed fourth diesel unit.

5 Dec 59

Operations – Routine operations, 21 practice intercepts.

6 Dec 59

Operations – Routine operations, 11 practice intercepts.

7 Dec 59

Operations – Broadcast Control, 6 PI’s.

Visits – Department of National Health and Welfare headed by Dr. Gash and Mr. Hamilton. W/C Hampson, F/L Howard and WO1 Crate accompanied.

8 Dec 59

Operations – Broadcast Control and AI-ECM exercises were held. 45 PI’s.

Visits – ADCHQ Supply Staff visit by S/L JR Low and F/L Swan.

9 Dec 59

Operations – Chain Shot, Broadcast Control and STP problem carried out. 25 PI’s.

10 Dec 59

Operations – Broadcast Control exercise held. 31 PI’s.

11 Dec 59

Operations – Broadcast Control exercise. 26 PI’s.

12 Dec 59

Operations – Routine operations, nil intercepts.

13 Dec 59

Operations – Routine operations, 32 PI’s.

14 Dec 59

Operations – Chain Shot exercise carried out, 33 PI’s.

15 Dec 59

Operations – Broadcast Control exercise, 15 PI’s.

16 Dec 59

Operations – Broadcast Control exercise and STP problem; 4 PI’s.

Recreation – Station bingo held.

17 Dec 59

Operations – Broadcast Control Exercise held, 38 PI’s

18 Dec 59

Operations – Routine operations, 24 PI’s.

19 Dec 59

Operations – Routine operations, nil intercepts.

Recreation – Annual Children’s Christmas Party took place.

20 Dec 59

Operations – Routine operations, 22 PI’s.

21 Dec 59

Operations – Routine operations, 11 PI’s.

22 Dec 59

Operations – Routine operations, nil intercepts.

23 Dec 59

Operations – Routine operations, nil intercepts.

26 Dec 59

Visits – Young Peoples Organization of Ste. Agathe visited the unit.

28 Dec 59

Operations – Routine operations, 27 PI’s.

29 Dec 59

Operations – Routine operations, 9 PI’s.

30 Dec 59

Operations – Routine operations, 8 PI’s.

1 Jan 60

Operations – Routine operations, nil intercepts.

2 Jan 60

Operations – Routine operations, 4 PI’s.

3 Jan 60

Operations – Routine operations, 10 PI’s.

4 Jan 60

Operations – Chain Shot and exercise Chess Match were held; 23 PI’s.

5 Jan 60

Operations – Counter Buzzer trials held, nil intercepts.

6 Jan 60

Operations – Routine operations, nil intercepts.

Construction & Engineering – New MSE Dispatch Office completed.

7 Jan 60

Operations – Routine operations, 4 PI’s.

Visits – G/C RE MacBride and Col. RJ Stevenson from WWRHR.

8 Jan 60

Operations – Routine operations, 21 PI’s.

9 Jan 60

Operations – Broadcast Control exercise held, 37 PI’s.

Recreation – Ski school for dependent children held by Miss B Bell.

10 Jan 60

Operations – Routine operations, 6 PI’s.

Recreation – St. Huberts Ladies basketball and badminton club arrived for tournament.

11 Jan 60

Operations – Routine operations, nil intercepts.

12 Jan 60

Operations – Routine operations, 35 PI’s.

Recreation – Curling tournament held at Chanticleer Club.

13 Jan 60

Operations – Routine operations, nil intercepts.

Telecommunications – STelO F/O Assad to Clinton for course on computers. RTT circuit was completed at TX-2 site.

14 Jan 60

Operations – Broadcast Control exercise and Cold Wind. Cocked Pistol at 1540Z, released at 1920Z. 27 PI’s.

15 Jan 60

Operations – Routine operations, nil intercepts.

16 Jan 60

Operations – Routine operations, nil intercepts.

17 Jan 60

Operations – AI-ECM carried out, 34 PI’s.

18 Jan 60

Operations – Chain Shot exercise held, 24 PI’s.

Visits – Philco representatives; Mr. Cottingham and Mr. Millar to do pre-installation checks on new height finder.

19 Jan 60

Operations – Routine operations, 13 PI’s.

20 Jan 60

Operations – Broadcast Control exercise, 11 PI’s.

21 Jan 60

Operations – Remote Control exercise held, 11 PI’s.

22 Jan 60

Operations – Cue Ball exercise, 11 PI’s.

Recreation – Airwomen volleyball team travelled to St. jean to compete in QRA tournament.

23 Jan 60

Operations – Routine operations, 10 PI’s.

24 Jan 60

Operations – Boneyard exercise held, 29 PI’s.

25 Jan 60

Operations – Routine operations, 22 PI’s.

26 Jan 60

Operations – AI-ECM Boneyard exercise; 22 PI’s.

27 Jan 60

Operations – Exercise Chain Shot carried out; 22 PI’s.

28 Jan 60

Operations – Routine operations today.

29 Jan 60

Operations – Routine operations.

30 Jan 60

Operations – Routine operations, 4 PI’s.

31 Jan 60

Operations – Routine operations, 6 PI’s.

1 Feb 60

Operations – Routine operations, 23 PI’s.

2 Feb 60

Operations – Routine operations, nil PI’s.

Visits – Mr. Sam Etchevery visited the unit.

3 Feb 60

Operations – Routine operations, nil PI’s.

Recreation – Bingo held tonight.

4 Feb 60

Operations – Remote Control exercise held, 21 PI’s. First shipment of FPS-6 radome received.

5 Feb 60

Operations – Remote control exercise held, 35 PI’s.

6 Feb 60

Operations – Routine operations, nil intercepts.

7 Feb 60

Operations – Routine operations, 6 PI’s.

8 Feb 60

Operations – Remote Control exercise held, 15 PI’s.

9 Feb 60

Operations – Chain Shot exercise held, 11 PI’s.

10 Feb 60

Operations – Routine operations, 2 PI’s.

11 Feb 60

Operations – Routine operations, nil intercepts.

12 Feb 60

Operations – Exercise Cold Wind carried out; 18 PI’s.

13 Feb 60

Operations – Routine operations, 19 PI’s.

Recreation – Airwomen’s Basketball travelling to St. Sylvestre for QRA meet.

14 Feb 60

Operations – Routine operations, nil intercepts.

15 Feb 60

Operations – Chain Shot exercise held, 18 PI’s.

16 Feb 60

Operations – Routine operations, 20 PI’s.

17 Feb 60

Operations – Chain Shot exercise held and remote control; 22 PI’s.

Recreation – Station bingo held.

18 Feb 60

Operations – Cue Ball exercise carried out, 11 PI’s.

Visit – Mr. George Myhill and party from AMC arrived to evaluate their spectrum analyzer.

19 Feb 60

Operations – Routine operations, nil PI’s.

20 Feb 60

Operations – Routine operations, 12 PI’s.

21 Feb 60

Operations – Routine operations, 21 PI’s.

22 Feb 60

Operations – Routine operations, 18 PI’s.

Visit – S/L Keillard and F/L Howard from AFHQ conducted tests for radiation in radome and roof of Ops building.

23 Feb 60

Operations – Routine operations, 13 PI’s.

24 Feb 60

Operations – Routine operations, 13 PI’s.

25 Feb 60

Operations – Exercise Cats Eye held; 14 intercepts.

Visit – S/L JT Faulkner to familiarize with FPS-20.

26 Feb 60

Operations – Routine operations, nil intercepts.

27 Feb 60

Operations – Routine operations, nil intercepts.

28 Feb 60

Operations – Routine operations, 10 PI’s.

Visit – S/L Currie, Staff Chaplain – officiates at divine service

29 Feb 60

Operations – Exercise Chain Shot and routine operations; 24 PI’s.

Visit – ADCHQ evaluation team to conduct 3 day evaluation of FPS-20.

1 Mar 60

Operations – Routine operations, 16 PI’s.

2 Mar 60

Operations – Evaluation trials today; 13 PI’s.

Recreation – Station hockey, ladies and men’s basketball teams left for a five day trip.

3 Mar 60

Operations – Cue Ball exercise was carried out; 13 intercepts attempted.

4 Mar 60

Operations – Remote Control exercise; 11 intercepts.

5 Mar 60

Operations – Routine operations, 18 PI’s.

6 Mar 60

Operations – Routine operations, 20 PI’s.

7 Mar 60

Operations – Chain Shot exercise, 22 PI’s.

8 Mar 60

Operations – Boneyard 3 AI-ECM exercise; 46 PI’s.

9 Mar 60

Operations – Chain Shot and STP problem; 50 PI’s.

10 Mar 60

Cold Wind exercise carried out, 6 PI’s.

11 Mar 60

Operations – Routine operations, 8 PI’s.

Recreation – Station annual Winter Carnival held and Queen chosen.

13 Mar 60

Operations – Routine operations, nil intercepts.

14 Mar 60

Operations – Routine operations, 22 PI’s.

15 Mar 60

Operations – Routine operations, 12 PI’s.

16 Mar 60

Operations – Routine operations, 8 PI’s.

17 Mar 60

Operations – Fall out test; building sealed for 12 hour period to test effects on personnel with no outside air brought in; nil PI’s.

18 Mar 60

Operations – Boneyard AI-ECM exercise, 25 intercepts.

19 Mar 60

Operations – Routine operations, 12 PI’s.

20 Mar 60

Operations – Routine operations, 20 PI’s.

21 Mar 60

Operations – Exercise Chain Shot run, 30 PI’s during the day.

22 Mar 60

Operations – Boneyard AI-ECM and 3 hours of STP problem were carried out. 39 intercepts.

23 Mar 60

Operations – Exercise Chain Shot held, 2 intercepts.

24 Mar 60

Operations – Routine operations, 4 PI’s.

25 Mar 60

Operations – Exercise Sun Lamp took place, 7 intercepts.

26 Mar 60

Operations – Routine operations, nil intercepts.

Recreation – Volleyball team proceeded to St. Jean.

27 Mar 60

Operations – Routine operations, nil intercepts.

28 Mar 60

Operations – Chain Shot exercise run, 26 intercepts.

Visit – Radar evaluation was carried out on FPS-20 by team from ADC.

29 Mar 60

Operations – Exercise "White Lightning" carried out, 23 intercepts.

30 Mar 60

Operations – Routine operations, 12 PI’s.

1 Apr 60

Operations – Routine operations, 49 PI’s.

Visit – A/C Harvey to inspect the station.

Recreation – Station Hockey team travelled to St. Jean for QRA playdowns.

2 Apr 60

Operations – Routine operations, 21 PI’s.

3 Apr 60

Operations – Routine operations, 14 PI’s.

4 Apr 60

Operations – Routine operations, nil intercepts.

5 Apr 60

Operations – Remote Control exercise; 10 intercepts..

6 Apr 60

Operations – Exercise Chain Shot held, 9 PI’s.

Visit – W/C Monteith to inspect construction and engineering.

7 Apr 60

Operations – Routine operations, 17 intercepts.

8 Apr 60

Operations – Cue Ball exercise took place today, 12 intercepts.

9 Apr 60

Operations – Routine operations, 10 PI’s

10 Apr 60

Operations – Routine operations, 2 intercepts.

11 Apr 60

Operations – Boneyard ECM and Chain Shot exercise held; total of 20 intercepts today.

12 Apr 60

Operations – ECM exercise today; 39 intercepts attempted. FPS-508 inspected by Northern Electric prior to annual overhaul.

13 Apr 60

Operations – Cold Wind and a Remote Control exercise were held, 20 intercepts.

14 Apr 60

Operations – Routine operations, 13 intercepts.

Visit – Personnel from ADCHQ ADC AMC and RCA Victor arrived to discuss modification of FPS-507.

15 Apr 60

Operations – Routine operations, 33 intercepts.

16 Apr 60

Operations – Routine operations and Remote control exercise, 14 PI’s.

17 Apr 60

Operations – Remote control exercise, 4 intercepts attempted. High altitude tests conducted on FPS-508.

18 Apr 60

Operations – Routine operations, 5 PI’s.

19 Apr 60

Operations – Routine operations, 24 PI’s.

20 Apr 60

Operations – Chain Shot exercise took place, 12 PI’s.

Recreation – Last bingo till fall held.

21 Apr 60

Operations – Routine operations, 6 PI’s.

22 Apr 60

Operations – Routine operations, 26 PI’s.

23 Apr 60

Operations – Routine operations, 12 PI’s.

24 Apr 60

Operations – Routine operations, 12 PI’s.

25 Apr 60

Operations – Chain Shot exercise held, 36 PI’s today.

26 Apr 60

Operations – Remote Control exercise held, 26 PI’s.

27 Apr 60

Operations – Exercise Cats Eye took place, 29 intercepts attempted.

28 Apr 60

Operations – Cats Eye ECM today, 5 intercepts attempted.

29 Apr 60

Operations – First shipment of AN/FPS-507 equipment arrived.

30 Apr 60

Operations – Routine operations, nil intercepts.

1 May 60

Operations – Routine operations, 6 PI’s.

2 May 60

Operations – Chain Shot exercise held, 25 PI’s.

3 May 60

Operations – Routine operations and GCI site run, 22 PI’s.

4 May 60

Operations – AI-ECM with Boneyard, 40 PI’s.

Visit – Lt. General G de Rivals-Mageves, deputy CDT 4ATAF, G/C Diamond, Col. Hill and Lt. Col. Roussac, French AF.

5 May 60

Operations – Remote Control and routine operations, 25 PI’s.

6 May 60

Operations – Routine operations, nil intercepts.

7 May 60

Operations – Routine operations, 9 PI’s.

8 May 60

Operations – Routine operations, 4 intercepts.

9 May 60

Operations – Routine operations, nil intercepts.

10 – 12 May 60

Operations – Semi-Annual Maintenance.

13 May 60

Operations – Routine operations, nil intercepts.

14 May 60

Operations – Routine operations, nil intercepts.

15 May 60

Operations – Routine operations, 8 PI’s.

16 May 60

Operations – Routine operations.

Recreation – Women’s Auxiliary held a fashion show with spring and summer fashions.

17 May 60

Operations – Routine operations, 21 PI’s.

18 May 60

Operations – Routine operations, 30 PI’s.

19 May 60

Operations – Cue Ball exercise held. Cocked Pistol at 2235Z, 14 intercepts.

20 May 60

Operations – Routine operations, released from Cocked Pistol at 0345Z, 13 PI’s.

21 May 60

Operations – Routine operations, nil intercepts.

22 May 60

Operations – Routine operations, nil intercepts.

23 May 60

Operations – Routine operations, nil intercepts.

Recreation – The inter-section softball league commenced.

24 May 60

Operations – Routine operations and STP problem; 22 PI’s.

Visit – A/C Porter from RAF.

25 May 60

Operations – Routine operations, 18 PI’s.

26 May 60

Operations – Routine operations, nil intercepts.

27 May 60

Operations – Routine operations, 8 PI’s.

28 May 60

Operations – Routine operations, 12 PI’s.

Recreation – Soccer team travelled to Uplands.

29 May 60

Operations – Routine operations, nil intercepts.

Visits – Ste. Agathe Legion visited the unit.

30 May 60

Operations – Last piece of AN/CPS-6B left the unit.

31 May 60

Operations – S/L Hill appointed COpsO. Unit received the third shipment of AN/FPS-507.

Signed by:
(WC Smith) W/C
Commanding Officer