S949-105 TD2240 (CCE)
14 Sep 62
Min (3)
COR
Status of Construction
Gap Filler Radar Stations, Various
The status of construction at the various Gap Filler Radar Stations is listed on the attached Appendices "A", "B", "C" and "D". Until detailed reports are received for individual stations, it is impossible to provide the information requested on a complete site-by-site basis. The stations have been grouped according to their approximate overall average but individual percentages for line items will vary. The time required to complete the construction is also an approximate number of months after approval of the DND-8 to DCL. When an individual site is completed will depend on how quickly DCL renegotiates an individual contract and how quickly a contractor resumes construction.
The problems, which we will be confronted with as the result of the deferment of the programme, are as follows:
(RB Whiting) A/C
CCE
2-8702
Attas
PS Land acquisition is either completed or nearing completion on all 45 sites.
(RB Whiting) A/C
CCE